Skip to main content

Search narrows for new Purple Line builder after 1st one quit project

The long-promised Purple Line light rail in Maryland is still a work in progress after the general contractor quit the project last year, but the search for a new one is narrowing.

Maryland Secretary of Transportation Gregory Slater said Tuesday night that the choice of a new design-build firm has been whittled to three, and a final selection must wait until the fall.

“These three firms are right now putting together proposals, taking tours of the alignment, gathering more information, digging into the designs,” Slater told an online meeting of Purple Line NOW! — a sort of booster group for the light rail system that’s made up of business, labor, environmental and neighborhood interests.

In the meantime, the state is overseeing subcontractors, who are mostly relocating utility lines but also working on the Plymouth Tunnel in Silver Spring and the nearly complete Glenridge Operations and Maintenance building.

“We’ve been still doing plenty of work the last six months and you see that out there, while we’re waiting to select that new design build firm,” Slater said.

The 16-mile light rail from New Carrollton in Prince George’s County to Bethesda in Montgomery County has been an idea circulating for decades. The state agreed to a public-private partnership in 2016; ground was broken in 2017; and the main contractor quit the project in September 2020 over what it said were $800 million in cost overruns.

Slater said progress is being made relocating utilities in the Silver Spring and Long Branch areas. Among the areas where utility relocation projects for the Purple Line are underway include Kenilworth Avenue, Riverdale Road and on the University of Maryland campus.

Work is continuing on the track bed and the walls of the Plymouth Tunnel in Silver Spring.
Slater told the group the Glenridge operations and maintenance center will be a key component of testing the rail cars when they are delivered.

Slater also told the meeting that the project is having to pay storage costs for completed rail cars at the manufacturer’s plant in Elmira, New York, because the project was unable to accept delivery of the cars at the contracted time. He did not say how much was the storage costs.

“We are going to finish this project and we are going to ride on the Purple Line. There is nothing in doubt about that,” Slater said.

Metro and IndyCar team up for a busy weekend of Freedom 250 Grand Prix events

No, you weren't hallucinating Thursday morning — that was an IndyCar being pulled along the Metro tracks through a portion of D.C. It was part of a promotion between the Freedom 250 Grand Prix and the Washington Metropolitan Area Transit Authority to remind people that the best way to navigate the expected huge crowds this weekend is to take Metro. "Even IndyCar knows the fastest way to get around is actually on Metro," said Randy Clarke, the transit agency's general manager and CEO. "We're really excited about this, and this car was a really kind of fun way to show a different way that people can see the Metro system, and we're having a little fun." The IndyCar, described as a work car that will not run in any of the races scheduled over the weekend, was fastened aboard a flat-bed train car and pulled along the yellow line, beginning at the King Street station up to the Mount Vernon station then back south to the L'Enfant Plaza station. Metro riders gawked at the multicolored, low-profile racecar as the train paused at L'Enfant for a photo op.