Digging starts for stalled Seattle tunnel machine

SEATTLE (AP) — Contractors building a new highway tunnel under downtown Seattle have started digging a 120-foot pit to rescue a stalled boring machine named Bertha.

Seattle Tunnel Partners also is pumping out groundwater as it digs the 80-foot-wide pit near the Seattle waterfront.

The $80 million, five-story-tall boring machine overheated and came to a stop last December after digging about 1,000 feet, or about 10 percent of the planned Highway 99 tunnel route. An investigation found seals in the cutting head were damaged.

A crane will lift the cutting head from the pit for repair. Tunneling could resume in March.

___

Information from: Seattle Daily Journal of Commerce, http://www.djc.com/

Copyright 2014 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Emergency guide: What you should do to prepare for emergencies

WASHINGTON — Do you know what you'd do if an emergency hits? What if you're at work, your spouse is stuck in traffic and your children are in school? There's no way to plan for every emergency, but you can make sure you're prepared for different scenarios, including making a plan for your family and building a kit of emergency supplies.